E.S.M. conducted an independent Functional Safety Assessment (FSA) for a remote power-generation control system upgrade. The assessment provided an objective review of whether the project’s functional safety activities and evidence supported a coherent, defensible safety case.
The upgrade replaced an ageing control system and introduced critical burner-management functions intended to satisfy the applicable requirements of AS 3814:2018.
The scope covered FSA 1 and FSA 2 under AS 61511.1, examining the adequacy of the functional safety planning, design and verification evidence at the relevant lifecycle stages.
The assessment examined whether the required functional safety lifecycle activities had been completed and whether the project evidence formed a consistent safety narrative. Evidence reviewed included the Functional Safety Management Plan; HAZOP and Layer of Protection Analysis (LOPA) reports; the SIL Selection Report and Safety Requirements Specification (SRS); PLC logic diagrams; the SIL verification report; and Factory Acceptance Test (FAT) procedures and records.
Each artefact was evaluated against the applicable clauses of AS 61511.1 to confirm that the required activities had been performed and adequately documented.
Beyond checking individual lifecycle phases, the assessment tested end-to-end traceability for each safety function, from hazard analysis and SIL selection through specification, implementation, verification and testing.
The independent review identified several issues requiring the design team’s immediate attention:
- Some implemented safety functions did not match the behaviour defined in the SRS and LOPA, potentially leaving the associated hazards without the intended protection.
- For some safety functions, the hardware model used in SIL verification did not align with the SRS. As a result, the calculated reliability and integrity could not demonstrate that the required SIL had been achieved.
- One safety function lacked sufficient FAT coverage to demonstrate correct operation across its full input range.
- A temperature-sensing function averaged the readings from all probes in a way that compromised the claimed redundancy.
The assessment demonstrated the value of independent review in maintaining a reliable safety case throughout a changing project. In fast-moving delivery environments, earlier lifecycle documents can become outdated and design decisions can drift from approved safety requirements. By identifying inconsistencies between the hazard analysis, specifications, verification calculations, implemented logic and test evidence, the FSA enabled the project team to correct critical gaps before the system was commissioned and operated.